U.S. regulator bars Freeport LNG plant restart over safety concerns

Freeport LNG, France, French

(Reuters) The second-biggest U.S. liquefied natural gas (LNG) export facility hit by fire earlier this month will not be allowed to repair or restart operations until it addresses risks to public safety, a pipeline regulator said on Thursday.

The June 8 blast and fire knocked out Freeport LNG’s 15 million tonnes per year (mtpa) Quintana plant, exacerbating global LNG shortages amid reduced gas flows from Russia while weighing heavily on domestic U.S. natural gas prices.

“Continued operation of Freeport’s LNG export facility without corrective measures may pose an integrity risk to public safety, property or the environment,” the U.S. Pipeline and Hazardous Materials Safety Administration (PHMSA) said in its preliminary report.

A problem with a safety valve led an 18-inch (46-cm) pipe with inner and outer stainless steel layers to overpressurize and burst, releasing LNG and methane that caused the blast, PHMSA said in its report.

It laid out a series of steps for investigating what caused a 300-foot (91-m) section of pipe to burst and release about 120,000 cubic feet of LNG.

The root cause analysis likely will delay a partial restart of the plant for 90 to 120 days, and could delay a full restart, analysts said.

Closely-held Freeport said it will continue working with PHMSA and other regulatory bodies to obtain the necessary approvals to restart operations. It estimated the resumption of partial liquefaction operations to be in early October and a return to full production by year-end.

U.S. natural gas futures tumbled 15% on Thursday due to the report and on a continued inventory build, contributing to a 33% price drop in June, the biggest monthly drop since 2018.

LENGTHY PROCESS

“The actual process (of reviews, repairs and approvals) will take longer than three months, and potentially take six to 12 months,” said Alex Munton, director of global gas and LNG at consultants Rapidan Energy Group.

But based on PHMSA’s past history, once it understands the cause of the blast and is confident in a repair plan, it likely will let a portion of the facility resume processing sooner, he said.

Freeport LNG has said the likely cause of the blast was an over-pressurized pipeline and that the equipment to chill natural gas into a liquid for export was not damaged.

The regulator ordered the company to submit within 60 days a plan for an outside investigator to provide a report on the extent of the damage to the facility. It did not say how long it would take to approve a plan. Freeport must also hire a third party to review the state of its LNG storage tanks.

Only after the reviews are completed can the company submit a plan to repair the damage, it said, further complicating Freeport LNG’s aim for a partial restart in September and full operation by year-end. (Reporting by Gary McWilliams Editing by Marguerita Choy)


Get the Weekly Newsletter Thousands of Mineral Rights Owners and Investors Rely On.
To Top
Lease or Sell Your Minerals Rights in Oklahoma or Texas ➡️(405) 492-6277

Have your oil & gas questions answered by industry experts.